Triangle Park Project Updates

Construction Status

  • Tree and brush removals: January 8-10

  • Culvert removal and installation of new:   January 15

  • Delivery/stockpile of Stone for stream channel rock riffle: January 15

  • Soil Excavation and Removal to Landfill: January 16 – Current

 

Project Timeline

  • Engineering Plans: Completed

  • Permit Review Completed

  • Bid Project: July-August 2018

  • Board Approval: Septmeber 2018

  • Construction Begins: Early January 2019

  • Construction Completion: End of March 2019