February 12, 2014 – At the February 10, 2015 regular board meeting, the Park Board accepted the low qualified bids and approved contract agreements for the Phase 1 Bids for excavation, site utilities and site concrete.
Bid Packages #1 – #3
Total Summary (Target Budget = $1,254,737)
Lenny Hoffman Excavating
Base bid: $686,547.00
Alternate bid #1: $6,000.00
Hoppies Landscaping
Base bid: $293,141.00
Alternate bid #1: Not Bid Upon
Abbey Paving
Base bid: $236,080.00
Alternate bid #1: Not Bid Upon
Total Bids: $1,215,768
The Phase 1 work will commence as soon as site conditions become suitable for construction operations, tentatively scheduled for March 2015.
The Park Board also authorized the letting of bids for the Phase 2 work specified for precast concrete, structural steel and building concrete. The Phase 2 bid package is tentatively scheduled for letting on February 25, 2015.
Remaining Phase 3 bid packages is tentatively schedule for letting mid to late March 2015.